Chrystal Street Repair Update Week 9

Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will be completed over the next two to three weeks.
|
Important dates |
Activity |
Impact to residents |
Affected households |
|
Monday, 13 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Tuesday, 14 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Wednesday, 15 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Thursday, 16 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Friday, 17 June 2022 |
Footpath construction |
No on street parking |
All households |
Take a look at what is happening around Richmond
Pickup and Plant at Pareaway Banks Avenue School Entrance
This school walkway at the Northern entrance of Pareawa Banks Avenue School needs tidying. So we ran a working bee!
RedZone Dogs Richmond Walking with The Walking Festival
We co-hosted a dogs walk with Red Zone Dogs, part of The Walking Festival. Get in touch if you want to join their dog walks!
Riverlution Ramble – Explore the Green Spine
We joined Hayley from Avon Otakaro Network on a Riverlution Ramble, showing everything happening in the Red Zone, part of the Walking Festival.
Richmond Gala 2026
Our Richmond Gala was another success. Thousands of people came for a great day out. We loved running the Children’s Play Area at Avebury Park.