Roading Richmond
Keep up to date with roading projects around our suburb.
Here is the latest report from the RRBA from their latest meeting with CCC staff about the roading issues in Richmond:
RICHMOND ROAD REPAIR UPDATES
Since a fiery meeting attended by residents and Council staff in 2018, the Richmond Residents’ and Business Association has been collaborating with the City Council with the aim of establishing a step-by-step road repair programme and general upgrade of Richmond streets. 31 separate projects were identified and gradual progress has been made working through these.
Roadworks Update for Nicholls Street 12
Traffic: Nicholls Street, Road closure. The footpath on the west side will remain open until the end of 24/04/24, after which pedestrian access will be switched to the east side. (Residents living on Nicholls st, regarding your access, please check Road Closure...
Roadworks Update for Nicholls Street 11
Traffic: Nicholls Street, Road closure. West side Footpath open. (Residents living on Nicholls st, regarding your access, please check Road Closure Disruption Minimisation Plan- Nicholl st 050424) Dudley street, one way at all time, no entry permitted on Stapleton...
Roadworks Update for Nicholls Street 10
Traffic: Nicholls Street one-way on 8/4-9/4, no entry permitted on North Avon RoadRoad closure from 10/4 Dudley street, one way at all time, no entry permitted on Stapleton Road. Inconvenience: #50,51,51A,1/53,2/53,54,55,57,58 (Kane will inform you the day before, to...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 8
Stapletons Road (Warden St to Shirley Rd). Work completed Remediated driveway at No.184 Completed basecourse construction Completed 90% of footpaths and driveway Installation of raised platform Work planned for the week ahead Asphalt final section of footpaths...
Roadworks Update for Nicholls Street 9
Traffic: Traffic on both Nicholls Street and Dudley street are set up as one-way, and no entry permitted on North Avon Road and Stapleton Road. Inconvenience: Property access including residents on East side of Nicholls st. We plan to do a kerb pour on Thurs, 4/4/24....
Roadworks Update for Nicholls Street 8
Traffic: Traffic on both Nicholls Street and Dudley street are set up as one-way, and no entry permitted on North Avon Road and Stapleton Road. Inconvenience: Property access including residents on East side of Nicholls st. We plan to do a kerb pour on Wed, 27/03/24....
Richmond Village Shopping Centre Pot Holes Fixed
After years of We are Richmond lobbying to get the Richmond Village Carpark restored to a usable standard, the potholes and damage have finally been patch-fixed by one of multiple landlords. Multiple residents and shoppers complained about the safety of this shopping...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 7
Stapletons Road (Warden St to Shirley Rd). COMPLETED Footpath preparation, ready for asphalt Road preparation. LOOK AHEAD Complete basecourse construction for the road Asphalt all footpaths and vehicle crossings. Begin installation of raised platform Chipseal of road...
Roadworks Update for Nicholls Street 7
Traffic: Traffic on both Nicholls Street and Dudley street are set up as one-way, and no entry permitted on NorthAvon Road and Stapleton Road. Inconvenience: Property access including residents on East side of Nicholls st. Disruption Management: Our plan includes...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 6
Stapletons Road (Warden St to Shirley Rd). COMPLETED Completed the final kerb pour Subbase construction now fully complete LOOK AHEAD Complete all footpath construction ready for asphalt Complete basecourse construction Delays None Take a look at what is happening...
Roadworks Update for Nicholls Street 6
Traffic: Traffic on both Nicholls Street and Dudley street are set up as one-way, and no entry permitted on NorthAvon Road and Stapleton Road. Inconvenience: Property access including residents on East side of Nicholls st. Disruption Management: Our plan includes...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 5
Stapletons Road (Warden St to Shirley Rd). COMPLETED Begun the Shirley Road/Stapletons Road intersection construction. Completed the second stage of road construction up to Shirley Road. Completed the Western side footpath works up to Shirley Road LOOK AHEAD Complete...
Roadworks Update for Nicholls Street 5
Traffic: Traffic on both Nicholls Street and Dudley street are set up as one-way, and no entry permitted on NorthAvon Road and Stapleton Road. Inconvenience: Property access including residents on East side of Nicholls st and 55 Nicholls st. You will receive aletter...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 4
Stapletons Road (Warden St to Shirley Rd). COMPLETED Completed the road dig out on Stapletons Road Asphalted the western side footpath up to Shirley Road Begun road construction LOOK AHEAD Begin the Shirley Road tie in works. Complete subbase construction Complete the...
Roadworks Update for Nicholls Street 4
Traffic: Traffic on both Nicholls Street and Dudley street are set up as one-way, and no entry permitted on North Avon Road and Stapleton Road. Inconvenience: Property access including west side of Nicolls Street and 58,60 Nicholls st may be impacted during this...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 3
Stapletons Road (Warden St to Shirley Rd). COMPLETED Begun excavating carriageway to the underside of the road construction and begin filling Constructed the Eastern side footpath up to Shirley Road ready for asphalt LOOK AHEAD Continue the road dig out on...
Roadworks Update for Nicholls Street 3
Traffic: Traffic on both Nicholls Street and Dudley street will be organized as one-way, and entry will not bepermitted on North Avon Road and Stapleton Road.Site truck exits the work a zone on Nicholls st towards Dudley with a traffic Controller (TC) who has a...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 2
Stapletons Road (Warden St to Shirley Rd) COMPLETED Drainage completed Western side footpath up to Shirley Road ready for asphalt Excavated Western side of the road to the underside of the road formation and begin road construction LOOK AHEAD Begin excavating...
Roadworks Update for Nicholls Street 2
Roadworks Update for Nicholls Street: Currently, the traffic management setup on Nicholls St allows for one-way traffic only from Dudley St towards North Avon Road. However, some residents on Nicholls St are turning in the wrong direction. To ensure everyone's safety,...
Roadworks Update for Nicholls Street 1
Roadworks Update for Nicholls Street: Traffic: Traffic on Nicholls Street will be organized as one-way, and entry will not be permitted on North Avon Road. Inconvenience: Property access for those situated on the west side of Nicholls Street, including Richmond...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd)
Roadworks Update for Stapletons Road (Warden St to Shirley Rd): COMPLETED Completed removal of kerb and channel on the Western side. Kerb foundation ready to pour next week. Drainage 70% completed LOOK AHEAD Pour the kerb and channel Complete drainage Begin...
Averill Street and Stapletons Road Work Updates 2023/24
Roadworks Update for the northern Richmond area: Isaac Construction Update on Progress in Averill Street:Work is progressing well and it is hoped the major work on the Stapletons/Averill intersection will be finished by the end of this week. Work will then move to the...
30km/hr Speed Reduction in Richmond–Safe Speed Neighbourhoods
Richmond has been the first suburb to change to 30km per hour speeds on certain streets. Why?
Richmond Roading Update 2023
The representatives of the Richmond Residents and Business Association met recently with the Transport and Roading Group at the Christchurch City Council and we are now able to pass on the following information.................. UPDATE ON IMPROVING THE RICHMOND...
Petrie Street Repair Update Week 18
The aim of the following week will be to finish the road construction and complete its final surface . The road closure should only remain in place for 2 more weeks. In the last week, we will complete the line marking and final touch-ups for the handover back to the...
Petrie Street Repair Update Week 17
Unfortunately, the footpath asphalt couldn’t get completed this week due to the moisture in the materials. We have reprogramed this for Monday--dependent on the weekend's weather. The aim of this week will be to finish the Eastern side and preparing the road for its...
Petrie Street Repair Update Week 16
The aim of this week will be to finish the Eastern side, and also planning for preparing the road for its final surface . Pedestrians will remain on the new footpath on the East side. As Always, if you have any concerns about parking, deliveries you may be expecting,...
Petrie Street Repair Update Week 15
The aim of the following week will be the final touch-ups of the Western side whilst we carry on preparing the footpath and driveway crossings on the Eastern side. We will also be installing the new storm water connections and planting of trees and shrubs along the...
Petrie Street Repair Update Week 14
Week 14 Aim of the this week's work will be working to complete the Western side of the street whilst we install the new kerbing and prepare for the new footpath on the Eastern side. We will also complete the installation of the new Stormwater pipes crossing the road....
Petrie Street Repair Update Week 12
The aim of the following week will be to complete the entire road excavation. Residents will be moved the West side of the street as we progress with the road construction on the East side. Last week the footpath contained too much moisture for Asphalt sealing, so we...
Petrie Street Repair Update Week 11
This week sees two important milestones. The connection of the water main on North Avon Road and commencing the road construction. The road construction is key to delivering the project on time so expect some additional resource to arrive to site to help with these...
Petrie Street Repair Update Week 8
As most residents on our street are aware we had anticipated changing our traffic management arrangement this week to help shorten our programme of works. Unfortunately other traffic arrangements in the area has meant we need to put this approach on hold for another...
Petrie Street Repair Update Week 7
Main aim for week 7 is to allow the watermain advance towards Randall. Having lost one day to rain last week we are anticipating laying the new pipe up to property No.32. The watermain is welded into “strings” each 36m long. We will endeavour to keep them from your...
Petrie Street Repair Update Week 6
Firstly, I would like to thank the residents for their help and support during week 5 which allowed us to pour the first section of new kerb and channel. It’s always a day of significant disruption and the residents were very helpful and supportive during this...
Petrie Street Repair Update Week 4
Week four sees us getting closer to the end of the street with the Stormwater drainage. The final 80 metres of this pipeline is reinforced concrete so this takes a bit longer as there’s some added detailing involved and concrete pouring around the pipe. Nevertheless,...
Chrystal Street Repair Update Planting
From Liam Cai, ISAAC Project Manager: Our landscaping contractor plans to complete the berm and hydroseed today on 2 August. However, due to the wet weather and saturated soil, we have to delay the tree planting when we assess the soil dampness. Currently we’ve...
Chrystal Street Repair Update Week 9
Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will be completed over the next two to...
Petrie Street Repair Update Week 3
Week 3 see’s our drainage team pass the 50% complete mark for the new stormwater line. The team will continue straight down Petrie toward No.13. At times this will involve trenching past residents driveways so expect a knock from our friendly staff the evening or...
Chrystal Street Repair Update Week 8
Week 8 work plan and the key dates and impact below. We are planning for chipseal tomorrow but will make the final decision in the morning based on the ground temperature and weather forecast. Most of the construction will be finished after the chipseal, we will ramp...
Chrystal Street Repair Update Week 7
Week 7 work plan and the key dates and impact below. Chipseal of the carriageway is Wed 8 June and we will not be able to provide access for vehicles during the sealing, only after 4:30pm. We’d would like to maintain the road closure to public for the next two weeks...
Petrie Street Repair Update Week 2
Week 2 Petrie Street Works: Important dates Activity Impact to residents Affected households Monday, 30 May 2022 New 300mm Underchannel Stormwater Pipe One Way system Northbound between North Avon and Randall. Driveway access maintained throughout Residents between...
Chrystal Street Repair Update Week 6
Week 6 work plan and the key dates and impact below. We will still focus on road excavation and pavement construction. In addition, we will excavate and install stormwater pipe across the road in front to No. 17 and No. 19. in this week. Important dates...
Chrystal Street Repair Update Week 5
Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager. We appreciate that everyone has put up with the inconvenience caused by the construction. We are glad to see the new road configuration start to...
Richmond Road Repair Update
Since a fiery meeting attended by residents and Council staff in 2018, the Richmond Residents’ and Business Association has been collaborating with the City Council with the aim of establishing a step-by-step road repair programme and general upgrade of Richmond...
RR&BA gets quick action from council after local slips on icy bridge
Community Action gets mesh put on Guild Street bridge
Richmond Road Repair Project Update
An update on Richmond roading projects from contractor Mike Downs
Petrie / Stapletons / Randall St roadworks
An update on Richmond roading projects from contractor Mike Downs