On April 11, the Laura Fergusson Trust held an informal gathering in the grounds of the old site of Marian College. A group from “We Are Richmond” were invited to attend along with the Mayor, Liane Dalziel, city councillors and trust board members of the Laura Fergusson Trust.

The CEO of the Trust, Kathryn Jones, provided the background to the proposed move from their current site near Jellie Park to this new site in Richmond. The incidence of brain injury was described as reaching pandemic levels as new knowledge and research methods are developed beside a growing awareness of the implications of head injuries. The new centre will provide accommodation for dependent patients and a number of patients for shorter periods of treatment and rehabilitation. They will also be able to centralise their services which are currently meeting the needs of over a thousand patients a day.

This is a major financial undertaking by the Trust and “We Are Richmond” are proud to be working alongside them as they seek to establish their identity in our area. The Trust are hopeful that the new complex will be operational by 2026/27 as they move through many complex processes surrounding consents, building design, and financial support.

By David Duffy

For more information on the Laura Fergusson Brain Injury Trust, click here.

 

WE ARE RICHMOND

Petrie Street Repair Update Week 12

Petrie Street Repair Update Week 12

The aim of the following week will be to complete the entire road excavation. Residents will be moved the West side of the street as we progress with the road construction on the East side. Last week the footpath contained too much moisture for Asphalt sealing, so we...

read more
Chrystal Street Repair Update Planting

Chrystal Street Repair Update Planting

From Liam Cai, ISAAC Project Manager: Our landscaping contractor plans to complete the berm and hydroseed today on 2 August. However, due to the wet weather and saturated soil, we have to delay the tree planting when we assess the soil dampness. Currently we’ve...

read more
Petrie Street Repair Update Week 11

Petrie Street Repair Update Week 11

This week sees two important milestones. The connection of the water main on North Avon Road and commencing the road construction. The road construction is key to delivering the project on time so expect some additional resource to arrive to site to help with these...