Petrie Park Update December 2023
By Hayley Guglietta
The Petrie Park bowling club remediation is well and truly underway. We have completed the first round of soil testing which has indicated higher than normal levels of arsenic, especially around where the old bowling club shed used to be. High levels of arsenic were expected, given the chemicals used to maintain bowling greens across the country.
If you get a chance, pop on down to the southern half of Petrie Park and check out our progress. There are also signs dotted around the southern portion of the fence.
WE ARE RICHMOND
Roadworks Update for Nicholls Street 14
Two kerb pours are scheduled this week. The first, on Wednesday, is for the North Avon Road Kerb island, with a diamond Traffic management setup for the entire week. Residents of Nicholls Street will not be able to make a right turn onto North Avon Road during this...
Richmond Road Repair Programme Update
We have a recent update from Council about our road building programme which wasstarted in 2018. Currently, work is well underway in Nicholls and Dudley Streets for theStreet renewal project. It is hoped to have a new footpath along the eastern side of NichollsStreet...
Roadworks Update for Nicholls Street 13
Traffic: Nicholls Street, Road closure. The footpath on the west side will remain open until the end of 29/04/24, after which pedestrian access will be switched to the east side. (Residents living on Nicholls st, regarding your access, please check Road Closure...