Averill Street and Stapletons Road Work Updates 2023/24
Roadworks Update for the northern Richmond area:
Isaac Construction Update on Progress in Averill Street:
Work is progressing well and it is hoped the major work on the Stapletons/Averill intersection will be finished by the end of this week. Work will then move to the Petrie/Averill intersection next week. Work on the Petrie/Averill intersection will be completed by 22 December.
Stapletons Road rebuild – Warden St to Shirley Road:
Residents in Stapletons Road and nearby including aged care centres, early childhood centres and schools can expect a mail drop from Corde explaining the timeline for the work to begin in this area of Richmond soon. Preliminary surveying work will be done before Christmas and the major reconstruction programme will begin on January 8. Up to date weekly programme schedules will be published on our Facebook site each week so that residents can make plans to cover access to properties during the road closure periods.
Averill Street and Stapletons Road Work Updates 2023/24
Take a look at what is happening around Richmond
Cultivate comes to Richmond
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late
Adventure Ave, a family-friendly environmental playground for kids to enjoy and let their imaginations run wild.
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late
Petrie Park Barbecue – Summer with your Neighbours
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late
Activities at Richmond Working Men’s Club
Did you know the Richmond Working Men’s club has a Pigeon club!?
Cycle or walk the river
Jump on the Avon – Otakaro cycle/walkway and enjoy nature
Yoga At Avebury
Come down to Avebury House to enjoy yoga with Dakota.