Chrystal Street Repair Update Week 5

May 17, 2022 | Roading in Richmond

Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager.

We appreciate that everyone has put up with the inconvenience caused by the construction. We are glad to see the new road configuration start to take in shape as most of kerb & channel has been poured.

The focus of next two weeks is on road excavation and pavement construction. We plan to excavate east side of the traffic lane from Tuesday this week. We will continue to provide access to each households at the end of everyday and keep up with the communication.

 

Important dates Activity Impact to residents Affected households
Monday, 16 May 2022 Kerb base construction No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Tuesday, 17 May 2022 Milling on east side traffic lane No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Wednesday, 18 May 2022 Milling on east side traffic lane No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Road excavation and backfill
Thursday, 19 May 2022 Kerb pour & Backfill No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Road excavation and backfill
Friday, 20 May 2022 Road excavation and backfill No access to driveway between 7:30am and 5:30pm All households
Please note general impact on street residents still applies.  

Take a look at what is happening around Richmond

Petrie Street Repair Update Week 12

Petrie Street Repair Update Week 12

The aim of the following week will be to complete the entire road excavation. Residents will be moved the West side of the street as we progress with the road construction on the East side. Last week the footpath contained too much moisture for Asphalt sealing, so we...

read more
Petrie Street Repair Update Week 11

Petrie Street Repair Update Week 11

This week sees two important milestones. The connection of the water main on North Avon Road and commencing the road construction. The road construction is key to delivering the project on time so expect some additional resource to arrive to site to help with these...

read more
Petrie Street Repair Update Week 8

Petrie Street Repair Update Week 8

As most residents on our street are aware we had anticipated changing our traffic management arrangement this week to help shorten our programme of works. Unfortunately other traffic arrangements in the area has meant we need to put this approach on hold for another...

read more
Petrie Street Repair Update Week 7

Petrie Street Repair Update Week 7

Main aim for week 7 is to allow the watermain advance towards Randall. Having lost one day to rain last week we are anticipating laying the new pipe up to property No.32. The watermain is welded into “strings” each 36m long. We will endeavour to keep them from your...

read more