Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager.

We appreciate that everyone has put up with the inconvenience caused by the construction. We are glad to see the new road configuration start to take in shape as most of kerb & channel has been poured.

The focus of next two weeks is on road excavation and pavement construction. We plan to excavate east side of the traffic lane from Tuesday this week. We will continue to provide access to each households at the end of everyday and keep up with the communication.

 

Important dates Activity Impact to residents Affected households
Monday, 16 May 2022 Kerb base construction No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Tuesday, 17 May 2022 Milling on east side traffic lane No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Wednesday, 18 May 2022 Milling on east side traffic lane No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Road excavation and backfill
Thursday, 19 May 2022 Kerb pour & Backfill No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Road excavation and backfill
Friday, 20 May 2022 Road excavation and backfill No access to driveway between 7:30am and 5:30pm All households
Please note general impact on street residents still applies.  

Take a look at what is happening around Richmond

Roadworks Update for Nicholls Street 3

Roadworks Update for Nicholls Street 3

Traffic: Traffic on both Nicholls Street and Dudley street will be organized as one-way, and entry will not bepermitted on North Avon Road and Stapleton Road.Site truck exits the work a zone on Nicholls st towards Dudley with a traffic Controller (TC) who has a...

read more
Roadworks Update for Nicholls Street 2

Roadworks Update for Nicholls Street 2

Roadworks Update for Nicholls Street: Currently, the traffic management setup on Nicholls St allows for one-way traffic only from Dudley St towards North Avon Road. However, some residents on Nicholls St are turning in the wrong direction. To ensure everyone's safety,...

read more
Roadworks Update for Nicholls Street 1

Roadworks Update for Nicholls Street 1

Roadworks Update for Nicholls Street: Traffic: Traffic on Nicholls Street will be organized as one-way, and entry will not be permitted on North Avon Road. Inconvenience: Property access for those situated on the west side of Nicholls Street, including Richmond...

read more