Chrystal Street Repair Update Week 5
Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager.
We appreciate that everyone has put up with the inconvenience caused by the construction. We are glad to see the new road configuration start to take in shape as most of kerb & channel has been poured.
The focus of next two weeks is on road excavation and pavement construction. We plan to excavate east side of the traffic lane from Tuesday this week. We will continue to provide access to each households at the end of everyday and keep up with the communication.
Important dates | Activity | Impact to residents | Affected households |
Monday, 16 May 2022 | Kerb base construction | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Tuesday, 17 May 2022 | Milling on east side traffic lane | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Wednesday, 18 May 2022 | Milling on east side traffic lane | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Road excavation and backfill | |||
Thursday, 19 May 2022 | Kerb pour & Backfill | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Road excavation and backfill | |||
Friday, 20 May 2022 | Road excavation and backfill | No access to driveway between 7:30am and 5:30pm | All households |
Please note general impact on street residents still applies. |
Take a look at what is happening around Richmond
Roadworks Update for Nicholls Street 3
Traffic: Traffic on both Nicholls Street and Dudley street will be organized as one-way, and entry will not bepermitted on North Avon Road and Stapleton Road.Site truck exits the work a zone on Nicholls st towards Dudley with a traffic Controller (TC) who has a...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 2
Stapletons Road (Warden St to Shirley Rd) COMPLETED Drainage completed Western side footpath up to Shirley Road ready for asphalt Excavated Western side of the road to the underside of the road formation and begin road construction LOOK AHEAD Begin excavating...
Roadworks Update for Nicholls Street 2
Roadworks Update for Nicholls Street: Currently, the traffic management setup on Nicholls St allows for one-way traffic only from Dudley St towards North Avon Road. However, some residents on Nicholls St are turning in the wrong direction. To ensure everyone's safety,...
Roadworks Update for Nicholls Street 1
Roadworks Update for Nicholls Street: Traffic: Traffic on Nicholls Street will be organized as one-way, and entry will not be permitted on North Avon Road. Inconvenience: Property access for those situated on the west side of Nicholls Street, including Richmond...