Chrystal Street Repair Update Week 5

May 17, 2022 | Roading in Richmond

Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager.

We appreciate that everyone has put up with the inconvenience caused by the construction. We are glad to see the new road configuration start to take in shape as most of kerb & channel has been poured.

The focus of next two weeks is on road excavation and pavement construction. We plan to excavate east side of the traffic lane from Tuesday this week. We will continue to provide access to each households at the end of everyday and keep up with the communication.

 

Important dates Activity Impact to residents Affected households
Monday, 16 May 2022 Kerb base construction No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Tuesday, 17 May 2022 Milling on east side traffic lane No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Wednesday, 18 May 2022 Milling on east side traffic lane No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Road excavation and backfill
Thursday, 19 May 2022 Kerb pour & Backfill No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Road excavation and backfill
Friday, 20 May 2022 Road excavation and backfill No access to driveway between 7:30am and 5:30pm All households
Please note general impact on street residents still applies.  

Take a look at what is happening around Richmond

Roadworks Update for Nicholls Street 26

Roadworks Update for Nicholls Street 26

As you can see, new hydroseeding and nursery plants and trees have been planted on Nicholls Street. The greenery is making Nicholls Street look lovely, so let's protect it by avoiding stepping on it. With Dudley Street under road closure, we will assist with your...

read more
Roadworks Update for Nicholls Street 25

Roadworks Update for Nicholls Street 25

By the end of next week, all landscape work on Nicholls Street should be completed, weather permitting. We are scheduled to pour the kerb on Thursday, 25/07/2024. Residents at 39, 41, 43, 47, and 51 Dudley Street, please move your vehicles by 7am. If you have any gas...

read more
Roadworks Update for Nicholls Street 24

Roadworks Update for Nicholls Street 24

We have landscaping works happening on Nicholls Street. If we could please avoid parking cars and walking on the berms.   15/07/24 - 19/07/24 (Mon- Fri) •Nicholls Street is open to residents with two lanes. Residents can enter/exit from North Avon Road. •Please...

read more