Chrystal Street Repair Update Week 5
Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager.
We appreciate that everyone has put up with the inconvenience caused by the construction. We are glad to see the new road configuration start to take in shape as most of kerb & channel has been poured.
The focus of next two weeks is on road excavation and pavement construction. We plan to excavate east side of the traffic lane from Tuesday this week. We will continue to provide access to each households at the end of everyday and keep up with the communication.
Important dates | Activity | Impact to residents | Affected households |
Monday, 16 May 2022 | Kerb base construction | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Tuesday, 17 May 2022 | Milling on east side traffic lane | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Wednesday, 18 May 2022 | Milling on east side traffic lane | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Road excavation and backfill | |||
Thursday, 19 May 2022 | Kerb pour & Backfill | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Road excavation and backfill | |||
Friday, 20 May 2022 | Road excavation and backfill | No access to driveway between 7:30am and 5:30pm | All households |
Please note general impact on street residents still applies. |
Take a look at what is happening around Richmond
Roadworks Update for Nicholls Street 19
Finally, we hit the big milestone. Nicholls Street is now sealed! Thanks for all your patience and efforts to cooperate with our work. Now, to ensure the longevity and quality of our new surface, we kindly need your support by following the guidelines below: ...
Roadworks Update for Nicholls Street 18
The chipseal between Dudley St and No.31 Nicholls St is being completed. Here is some useful guidelines to help ensure the longevity and quality of this new surface: Avoid Sharp Turns and Hard Braking: Abrupt maneuvers can dislodge the chips. Please drive smoothly and...
Roadworks Update for Nicholls Street 17
Traffic: •Nicholls Street, Road closure. Live footpath is on the east side of Nicholls street. •Dudley street, one way at all time, no entry permitted on Stapletons Road. Inconvenience •On Nicholls Street, Naasra test rescheduled, date (TBC). The testing truck will...
Roadworks Update for Nicholls Street 16
Due to the weather and ongoing staff sickness, the chipsealing has been rescheduled to next Wednesday, 29/5/2024. If the rain saturates the road and it's too wet for sealing, we've set backup dates for Thursday, 30/5/2024, and the following Wednesday, 5/6/2024. We'll...