Chrystal Street Repair Update Week 5
Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager.
We appreciate that everyone has put up with the inconvenience caused by the construction. We are glad to see the new road configuration start to take in shape as most of kerb & channel has been poured.
The focus of next two weeks is on road excavation and pavement construction. We plan to excavate east side of the traffic lane from Tuesday this week. We will continue to provide access to each households at the end of everyday and keep up with the communication.
Important dates | Activity | Impact to residents | Affected households |
Monday, 16 May 2022 | Kerb base construction | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Tuesday, 17 May 2022 | Milling on east side traffic lane | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Wednesday, 18 May 2022 | Milling on east side traffic lane | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Road excavation and backfill | |||
Thursday, 19 May 2022 | Kerb pour & Backfill | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Road excavation and backfill | |||
Friday, 20 May 2022 | Road excavation and backfill | No access to driveway between 7:30am and 5:30pm | All households |
Please note general impact on street residents still applies. |
Take a look at what is happening around Richmond
Roadworks Update for Nicholls Street 12
Traffic: Nicholls Street, Road closure. The footpath on the west side will remain open until the end of 24/04/24, after which pedestrian access will be switched to the east side. (Residents living on Nicholls st, regarding your access, please check Road Closure...
Roadworks Update for Nicholls Street 11
Traffic: Nicholls Street, Road closure. West side Footpath open. (Residents living on Nicholls st, regarding your access, please check Road Closure Disruption Minimisation Plan- Nicholl st 050424) Dudley street, one way at all time, no entry permitted on Stapleton...
Roadworks Update for Nicholls Street 10
Traffic: Nicholls Street one-way on 8/4-9/4, no entry permitted on North Avon RoadRoad closure from 10/4 Dudley street, one way at all time, no entry permitted on Stapleton Road. Inconvenience: #50,51,51A,1/53,2/53,54,55,57,58 (Kane will inform you the day before, to...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 8
Stapletons Road (Warden St to Shirley Rd). Work completed Remediated driveway at No.184 Completed basecourse construction Completed 90% of footpaths and driveway Installation of raised platform Work planned for the week ahead Asphalt final section of footpaths...