Chrystal Street Repair Update Week 5

May 17, 2022 | Roading in Richmond

Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager.

We appreciate that everyone has put up with the inconvenience caused by the construction. We are glad to see the new road configuration start to take in shape as most of kerb & channel has been poured.

The focus of next two weeks is on road excavation and pavement construction. We plan to excavate east side of the traffic lane from Tuesday this week. We will continue to provide access to each households at the end of everyday and keep up with the communication.

 

Important dates Activity Impact to residents Affected households
Monday, 16 May 2022 Kerb base construction No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Tuesday, 17 May 2022 Milling on east side traffic lane No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Wednesday, 18 May 2022 Milling on east side traffic lane No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Road excavation and backfill
Thursday, 19 May 2022 Kerb pour & Backfill No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Road excavation and backfill
Friday, 20 May 2022 Road excavation and backfill No access to driveway between 7:30am and 5:30pm All households
Please note general impact on street residents still applies.  

Take a look at what is happening around Richmond

Roadworks Update for Nicholls Street 9

Roadworks Update for Nicholls Street 9

Traffic: Traffic on both Nicholls Street and Dudley street are set up as one-way, and no entry permitted on North Avon Road and Stapleton Road. Inconvenience: Property access including residents on East side of Nicholls st. We plan to do a kerb pour on Thurs, 4/4/24....

read more
Roadworks Update for Nicholls Street 8

Roadworks Update for Nicholls Street 8

Traffic: Traffic on both Nicholls Street and Dudley street are set up as one-way, and no entry permitted on North Avon Road and Stapleton Road. Inconvenience: Property access including residents on East side of Nicholls st. We plan to do a kerb pour on Wed, 27/03/24....

read more
Richmond Village Shopping Centre Pot Holes Fixed

Richmond Village Shopping Centre Pot Holes Fixed

After years of We are Richmond lobbying to get the Richmond Village Carpark restored to a usable standard, the potholes and damage have finally been patch-fixed by one of multiple landlords. Multiple residents and shoppers complained about the safety of this shopping...

read more