Chrystal Street Repair Update Week 6

May 25, 2022 | Roading in Richmond

Week 6 work plan and the key dates and impact below.  We will still focus on road excavation and pavement construction. In addition, we will excavate and install stormwater pipe across the road in front to No. 17 and No. 19. in this week.

 

Important dates

Activity

Impact to residents

Affected households

Monday, 23 May 2022

Milling on west side traffic lane

No access to driveway between 7:30am and 5:30pm

All households

Kerb base construction

Stromwater pipe across street

Tuesday, 24 May 2022

Kerb pour & Backfill

No access to driveway between 7:30am and 5:30pm

All households

Stromwater pipe across street

Wednesday, 25 May 2022

Footpath construction

No access to driveway between 7:30am and 5:30pm

All households

Stromwater pipe across street

Road excavation and backfill

Thursday, 26 May 2022

Footpath construction

No access to driveway between 7:30am and 5:30pm

All households

Stromwater pipe across street

Road excavation and backfill

Friday, 27 May 2022

Pavement basecourse construction

No access to driveway between 7:30am and 5:30pm

All households

Please note general impact on street residents still applies.

   

 

Take a look at what is happening around Richmond

Red Zone Edge Housing Forum

Red Zone Edge Housing Forum

At the Red Zone Housing Forum, guest speakers covered future Red Zone housing topics, then those attending wrote down what should and shouldn’t be in the Red Zone edge housing areas.

read more