Chrystal Street Repair Update Week 6

Week 6 work plan and the key dates and impact below. We will still focus on road excavation and pavement construction. In addition, we will excavate and install stormwater pipe across the road in front to No. 17 and No. 19. in this week.
|
Important dates |
Activity |
Impact to residents |
Affected households |
|
Monday, 23 May 2022 |
Milling on west side traffic lane |
No access to driveway between 7:30am and 5:30pm |
All households |
|
Kerb base construction |
|||
|
Stromwater pipe across street |
|||
|
Tuesday, 24 May 2022 |
Kerb pour & Backfill |
No access to driveway between 7:30am and 5:30pm |
All households |
|
Stromwater pipe across street |
|||
|
Wednesday, 25 May 2022 |
Footpath construction |
No access to driveway between 7:30am and 5:30pm |
All households |
|
Stromwater pipe across street |
|||
|
Road excavation and backfill |
|||
|
Thursday, 26 May 2022 |
Footpath construction |
No access to driveway between 7:30am and 5:30pm |
All households |
|
Stromwater pipe across street |
|||
|
Road excavation and backfill |
|||
|
Friday, 27 May 2022 |
Pavement basecourse construction |
No access to driveway between 7:30am and 5:30pm |
All households |
|
Please note general impact on street residents still applies. |
|||
Take a look at what is happening around Richmond
Petrie Park BBQ and Consultation 2025
We hosted a BBQ for Petrie Park and an open consultation for the planting plan.
Te Oraka Community Pools Co-Hosted Cleanup 1
Volunteers from different Shirley, Richmond and Dallington had a first cleanup session at Te Oraka Community Pools
Walking Weedathon 4
A multi-area walking Weedathon around the streets of Richmond!
Warden Street School Alleyway Cleanup Session 1
A big cleanout for an overgrown school entrance that was abandoned for over a decade on Warden Street, Richmond.