Chrystal Street Repair Update Week 6
Week 6 work plan and the key dates and impact below. We will still focus on road excavation and pavement construction. In addition, we will excavate and install stormwater pipe across the road in front to No. 17 and No. 19. in this week.
Important dates |
Activity |
Impact to residents |
Affected households |
Monday, 23 May 2022 |
Milling on west side traffic lane |
No access to driveway between 7:30am and 5:30pm |
All households |
Kerb base construction |
|||
Stromwater pipe across street |
|||
Tuesday, 24 May 2022 |
Kerb pour & Backfill |
No access to driveway between 7:30am and 5:30pm |
All households |
Stromwater pipe across street |
|||
Wednesday, 25 May 2022 |
Footpath construction |
No access to driveway between 7:30am and 5:30pm |
All households |
Stromwater pipe across street |
|||
Road excavation and backfill |
|||
Thursday, 26 May 2022 |
Footpath construction |
No access to driveway between 7:30am and 5:30pm |
All households |
Stromwater pipe across street |
|||
Road excavation and backfill |
|||
Friday, 27 May 2022 |
Pavement basecourse construction |
No access to driveway between 7:30am and 5:30pm |
All households |
Please note general impact on street residents still applies. |
Take a look at what is happening around Richmond
Swanns Road Parklet Working Bee Part 2
The RRBA co-hosted a wonderful planting event at Swanns Road Parklet again midweek this time.
Swanns Road Parklet Working Bee Part 1
The RRBA co-hosted a wonderful planting event at Swanns Road Parklet
Adventure Avenue Wander/ Walking Festival
The Richmond community gathered at a bbq at Petrie Park to spend time together but also engage on what they would like to see on the former bowling green at the southern half of the park.
30km/hr Speed Reduction in Richmond–Safe Speed Neighbourhoods
Richmond has been the first suburb to change to 30km per hour speeds on certain streets. Why?