Week 6 work plan and the key dates and impact below. We will still focus on road excavation and pavement construction. In addition, we will excavate and install stormwater pipe across the road in front to No. 17 and No. 19. in this week.
Important dates |
Activity |
Impact to residents |
Affected households |
Monday, 23 May 2022 |
Milling on west side traffic lane |
No access to driveway between 7:30am and 5:30pm |
All households |
Kerb base construction |
|||
Stromwater pipe across street |
|||
Tuesday, 24 May 2022 |
Kerb pour & Backfill |
No access to driveway between 7:30am and 5:30pm |
All households |
Stromwater pipe across street |
|||
Wednesday, 25 May 2022 |
Footpath construction |
No access to driveway between 7:30am and 5:30pm |
All households |
Stromwater pipe across street |
|||
Road excavation and backfill |
|||
Thursday, 26 May 2022 |
Footpath construction |
No access to driveway between 7:30am and 5:30pm |
All households |
Stromwater pipe across street |
|||
Road excavation and backfill |
|||
Friday, 27 May 2022 |
Pavement basecourse construction |
No access to driveway between 7:30am and 5:30pm |
All households |
Please note general impact on street residents still applies. |
Take a look at what is happening around Richmond
The Critic Sports Bar Opening at Richmond Club, The Borough
The RRBA were honoured to attend Elmer’s Ōtautahi Elephant Trail opening Thursday night and see all of the amazing elephant designs.
Swanns Road Parklet Working Bee Part 2
The RRBA co-hosted a wonderful planting event at Swanns Road Parklet again midweek this time.
Swanns Road Parklet Working Bee Part 1
The RRBA co-hosted a wonderful planting event at Swanns Road Parklet
Richmond Gala–RRBA Engagement and Children’s Play Space
The Richmond community gathered at a bbq at Petrie Park to spend time together but also engage on what they would like to see on the former bowling green at the southern half of the park.