Chrystal Street Repair Update Week 6
Week 6 work plan and the key dates and impact below. We will still focus on road excavation and pavement construction. In addition, we will excavate and install stormwater pipe across the road in front to No. 17 and No. 19. in this week.
Important dates |
Activity |
Impact to residents |
Affected households |
Monday, 23 May 2022 |
Milling on west side traffic lane |
No access to driveway between 7:30am and 5:30pm |
All households |
Kerb base construction |
|||
Stromwater pipe across street |
|||
Tuesday, 24 May 2022 |
Kerb pour & Backfill |
No access to driveway between 7:30am and 5:30pm |
All households |
Stromwater pipe across street |
|||
Wednesday, 25 May 2022 |
Footpath construction |
No access to driveway between 7:30am and 5:30pm |
All households |
Stromwater pipe across street |
|||
Road excavation and backfill |
|||
Thursday, 26 May 2022 |
Footpath construction |
No access to driveway between 7:30am and 5:30pm |
All households |
Stromwater pipe across street |
|||
Road excavation and backfill |
|||
Friday, 27 May 2022 |
Pavement basecourse construction |
No access to driveway between 7:30am and 5:30pm |
All households |
Please note general impact on street residents still applies. |
Take a look at what is happening around Richmond
Families Brighten Up the Vogel Street Alleyway
We Are Richmond team encourages local families to get their artist on
Avon Hub Now Open in Former Spartan Sport Hall
The Avon Hub held an open day 22 May to show the community the sport and meeting facilities now available.
Cultivate comes to Richmond
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late
Adventure Ave, a family-friendly environmental playground for kids to enjoy and let their imaginations run wild.
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late