Chrystal Street Repair Update Week 6
Week 6 work plan and the key dates and impact below. We will still focus on road excavation and pavement construction. In addition, we will excavate and install stormwater pipe across the road in front to No. 17 and No. 19. in this week.
Important dates |
Activity |
Impact to residents |
Affected households |
Monday, 23 May 2022 |
Milling on west side traffic lane |
No access to driveway between 7:30am and 5:30pm |
All households |
Kerb base construction |
|||
Stromwater pipe across street |
|||
Tuesday, 24 May 2022 |
Kerb pour & Backfill |
No access to driveway between 7:30am and 5:30pm |
All households |
Stromwater pipe across street |
|||
Wednesday, 25 May 2022 |
Footpath construction |
No access to driveway between 7:30am and 5:30pm |
All households |
Stromwater pipe across street |
|||
Road excavation and backfill |
|||
Thursday, 26 May 2022 |
Footpath construction |
No access to driveway between 7:30am and 5:30pm |
All households |
Stromwater pipe across street |
|||
Road excavation and backfill |
|||
Friday, 27 May 2022 |
Pavement basecourse construction |
No access to driveway between 7:30am and 5:30pm |
All households |
Please note general impact on street residents still applies. |
Take a look at what is happening around Richmond
Petrie Park Barbecue – Summer with your Neighbours
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late
Activities at Richmond Working Men’s Club
Did you know the Richmond Working Men’s club has a Pigeon club!?
Cycle or walk the river
Jump on the Avon – Otakaro cycle/walkway and enjoy nature
Yoga At Avebury
Come down to Avebury House to enjoy yoga with Dakota.