Chrystal Street Repair Update Week 7

Week 7 work plan and the key dates and impact below. Chipseal of the carriageway is Wed 8 June and we will not be able to provide access for vehicles during the sealing, only after 4:30pm.
We’d would like to maintain the road closure to public for the next two weeks and allow time for the new surfacing to settle. The residents can access their houses (enter from Randell St and exit at North Avon Road) while our crew is carrying on the footpath, berm and landscaping on both sides of the street.
| Important dates | Activity | Impact to residents | Affected households |
| Monday, 30 May 2022 | Road construction | No access to driveway between 7:30am and 5:30pm | All households |
| Footpath construction | |||
| Tuesday, 31 May 2022 | Road construction | No access to driveway between 7:30am and 5:30pm | All households |
| Footpath construction | |||
| Wednesday, 1 June 2022 | Road construction | No access to driveway between 7:30am and 5:30pm | All households |
| Footpath construction | |||
| Thursday, 2 June 2022 | Road construction | No access to driveway between 7:30am and 5:30pm | All households |
| Footpath construction | |||
| Friday, 3 June 2022 | Road construction | No access to driveway between 7:30am and 5:30pm | All households |
| Footpath construction | |||
| Please note general impact on street residents still applies. | |||
Take a look at what is happening around Richmond
Laura Fergusson Brain Injury Trust Groundbreaking Ceremony
Welcome Laura Fergusson Brain Injury Trust to our wider communities. We are excited for your presence in our area.
Te Oraka Community Pools Co-Hosted Fence Removal
Volunteers were back, from different Shirley, Richmond and Dallington groups to remove the Te Oraka Community Pool fence. Kai Pai!
Matariki Decoration Session 2
Second of two workshops to make fabric decorations for our Ururangi tree, celebrating Matariki.
Matariki Decoration Session 1
One of two workshops to make fabric decorations for our Ururangi tree, celebrating Matariki.