Chrystal Street Repair Update Week 7

Week 7 work plan and the key dates and impact below. Chipseal of the carriageway is Wed 8 June and we will not be able to provide access for vehicles during the sealing, only after 4:30pm.
We’d would like to maintain the road closure to public for the next two weeks and allow time for the new surfacing to settle. The residents can access their houses (enter from Randell St and exit at North Avon Road) while our crew is carrying on the footpath, berm and landscaping on both sides of the street.
| Important dates | Activity | Impact to residents | Affected households |
| Monday, 30 May 2022 | Road construction | No access to driveway between 7:30am and 5:30pm | All households |
| Footpath construction | |||
| Tuesday, 31 May 2022 | Road construction | No access to driveway between 7:30am and 5:30pm | All households |
| Footpath construction | |||
| Wednesday, 1 June 2022 | Road construction | No access to driveway between 7:30am and 5:30pm | All households |
| Footpath construction | |||
| Thursday, 2 June 2022 | Road construction | No access to driveway between 7:30am and 5:30pm | All households |
| Footpath construction | |||
| Friday, 3 June 2022 | Road construction | No access to driveway between 7:30am and 5:30pm | All households |
| Footpath construction | |||
| Please note general impact on street residents still applies. | |||
Take a look at what is happening around Richmond
Richmond Gala 2025
So much fun at Richmond Gala! Co-hosted with Avebury House and Richmond Community Garden, the Children’s Play Area (facilitated by We are Richmond) is always popular in Avebury Park.
Petrie Park BBQ and Consultation 2025
We hosted a BBQ for Petrie Park and an open consultation for the planting plan.
Te Oraka Community Pools Co-Hosted Cleanup 1
Volunteers from different Shirley, Richmond and Dallington had a first cleanup session at Te Oraka Community Pools
Walking Weedathon 4
A multi-area walking Weedathon around the streets of Richmond!