Chrystal Street Repair Update Week 7
Week 7 work plan and the key dates and impact below. Chipseal of the carriageway is Wed 8 June and we will not be able to provide access for vehicles during the sealing, only after 4:30pm.
We’d would like to maintain the road closure to public for the next two weeks and allow time for the new surfacing to settle. The residents can access their houses (enter from Randell St and exit at North Avon Road) while our crew is carrying on the footpath, berm and landscaping on both sides of the street.
Important dates | Activity | Impact to residents | Affected households |
Monday, 30 May 2022 | Road construction | No access to driveway between 7:30am and 5:30pm | All households |
Footpath construction | |||
Tuesday, 31 May 2022 | Road construction | No access to driveway between 7:30am and 5:30pm | All households |
Footpath construction | |||
Wednesday, 1 June 2022 | Road construction | No access to driveway between 7:30am and 5:30pm | All households |
Footpath construction | |||
Thursday, 2 June 2022 | Road construction | No access to driveway between 7:30am and 5:30pm | All households |
Footpath construction | |||
Friday, 3 June 2022 | Road construction | No access to driveway between 7:30am and 5:30pm | All households |
Footpath construction | |||
Please note general impact on street residents still applies. |
Take a look at what is happening around Richmond
Planting for the Future
Over 360 Pareawa Banks Avenue students and local organisations come together to plant trees for the future.
Rainwater Garden Planting Session on Stanmore Road
Rainwater Garden Brings Beauty to Busy Road
Mayoral Candidate/ Mural Painting Event a Success
We Are Richmond team encourages locals to meet political candidates and paint!
Second Community Painting Event at Vogel Street Alleyway a Success
We Are Richmond team encourages local families to get their artist on for a second time