Chrystal Street Repair Update Week 8

Jun 7, 2022 | Roading in Richmond

Week 8 work plan and the key dates and impact below. We are planning for chipseal tomorrow but will make the final decision in the morning based on the ground temperature and weather forecast. Most of the construction will be finished after the chipseal, we will ramp down to one or two crews working on the footpath, berm and landscaping in the following two to three weeks. On street parking will become available gradually as we complete the footpath and berm/landscaping.

 

Important dates

Activity

Impact to residents

Affected households

Tuesday, 7 June 2022

Chipseal

No access to the street during chipseal
No on street parking

All households

Footpath construction

Wednesday, 8 June 2022

Footpath construction

No on street parking

All households

Thursday, 9 June 2022

Footpath construction

No on street parking

All households

Friday, 10 June 2022

Footpath construction

No on street parking

All households

Please note general impact on street residents still applies.

 

Take a look at what is happening around Richmond

Matariki 2024 — A Day and Night of Connection

Matariki 2024 — A Day and Night of Connection

Matariki in the Zone was a wonderful day and evening out for our community. A big thank you to Avon-Ōtākaro Network Richmond Community Garden and Avebury House for running this every year! We are Richmond hopped on the bandwagon to help out more this year.   So...

read more