Chrystal Street Repair Update Week 8

Week 8 work plan and the key dates and impact below. We are planning for chipseal tomorrow but will make the final decision in the morning based on the ground temperature and weather forecast. Most of the construction will be finished after the chipseal, we will ramp down to one or two crews working on the footpath, berm and landscaping in the following two to three weeks. On street parking will become available gradually as we complete the footpath and berm/landscaping.
|
Important dates |
Activity |
Impact to residents |
Affected households |
|
Tuesday, 7 June 2022 |
Chipseal |
No access to the street during chipseal |
All households |
|
Footpath construction |
|||
|
Wednesday, 8 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Thursday, 9 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Friday, 10 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Please note general impact on street residents still applies. |
|||
Take a look at what is happening around Richmond
Meet-Your-Neighbours Tidy Up Session at Medway Parklet
The Medway Parklet needed a good tidy and local neighbours wanted to meet to see if they could maintain this area in the future.
Vape Information Community Talk
Anna Stewart of Vape-Free Kids NZ spoke to the community about vape’s effects and regulations in New Zealand.
Spring Fair 2025
The RRBA had a fabulous day helping run the Spring Fair alongside Avebury House and Richmond Community Garden. They helped activate the children’s play area and also interacted with the public at their infomation stall.
Meet-the-Candidates for Central Ward Councillor
Meet the Candidates for Central Ward Councillor candidates was a successful evening, co-hosted by Sunrise Rotary, We are Richmond and Phillipstown Hub