Chrystal Street Repair Update Week 8

Week 8 work plan and the key dates and impact below. We are planning for chipseal tomorrow but will make the final decision in the morning based on the ground temperature and weather forecast. Most of the construction will be finished after the chipseal, we will ramp down to one or two crews working on the footpath, berm and landscaping in the following two to three weeks. On street parking will become available gradually as we complete the footpath and berm/landscaping.
|
Important dates |
Activity |
Impact to residents |
Affected households |
|
Tuesday, 7 June 2022 |
Chipseal |
No access to the street during chipseal |
All households |
|
Footpath construction |
|||
|
Wednesday, 8 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Thursday, 9 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Friday, 10 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Please note general impact on street residents still applies. |
|||
Take a look at what is happening around Richmond
Petrie Park Community BBQ & Engagement Session
The Richmond community gathered at a bbq at Petrie Park to spend time together but also engage on what they would like to see on the former bowling green at the southern half of the park.
Safe Speed Neighbourhoods Submission
The implementation of the new speed limits would fit well with the current traffic improvement initiatives in Richmond.
Planting for the Future
Over 360 Pareawa Banks Avenue students and local organisations come together to plant trees for the future.
Rainwater Garden Planting Session on Stanmore Road
Rainwater Garden Brings Beauty to Busy Road



