Chrystal Street Repair Update Week 8
Week 8 work plan and the key dates and impact below. We are planning for chipseal tomorrow but will make the final decision in the morning based on the ground temperature and weather forecast. Most of the construction will be finished after the chipseal, we will ramp down to one or two crews working on the footpath, berm and landscaping in the following two to three weeks. On street parking will become available gradually as we complete the footpath and berm/landscaping.
Important dates |
Activity |
Impact to residents |
Affected households |
Tuesday, 7 June 2022 |
Chipseal |
No access to the street during chipseal |
All households |
Footpath construction |
|||
Wednesday, 8 June 2022 |
Footpath construction |
No on street parking |
All households |
Thursday, 9 June 2022 |
Footpath construction |
No on street parking |
All households |
Friday, 10 June 2022 |
Footpath construction |
No on street parking |
All households |
Please note general impact on street residents still applies. |
Take a look at what is happening around Richmond
Petrie Park BBQ & Planting Event
The Richmond community gathered at a bbq at Petrie Park to spend time together but also engage on what they would like to see on the former bowling green at the southern half of the park.
RRBA Seeks Local Graphic Designer
If you are a graphic designer living in the Richmond area, please get in touch!
Spring Fair 2023 Was a Success!
The RRBA had a fabulous day helping run the Spring Fair alongside Avebury House and Richmond Community Garden. They helped activate the children’s play area and also interacted with the public at their infomation stall.
30km/hr Speed Reduction in Richmond–Safe Speed Neighbourhoods
Richmond has been the first suburb to change to 30km per hour speeds on certain streets. Why?