Chrystal Street Repair Update Week 8

Week 8 work plan and the key dates and impact below. We are planning for chipseal tomorrow but will make the final decision in the morning based on the ground temperature and weather forecast. Most of the construction will be finished after the chipseal, we will ramp down to one or two crews working on the footpath, berm and landscaping in the following two to three weeks. On street parking will become available gradually as we complete the footpath and berm/landscaping.
Important dates |
Activity |
Impact to residents |
Affected households |
Tuesday, 7 June 2022 |
Chipseal |
No access to the street during chipseal |
All households |
Footpath construction |
|||
Wednesday, 8 June 2022 |
Footpath construction |
No on street parking |
All households |
Thursday, 9 June 2022 |
Footpath construction |
No on street parking |
All households |
Friday, 10 June 2022 |
Footpath construction |
No on street parking |
All households |
Please note general impact on street residents still applies. |

Take a look at what is happening around Richmond
Second Community Painting Event at Vogel Street Alleyway a Success
We Are Richmond team encourages local families to get their artist on for a second time
Families Brighten Up the Vogel Street Alleyway
We Are Richmond team encourages local families to get their artist on
Cultivate comes to Richmond
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late
Adventure Ave, a family-friendly environmental playground for kids to enjoy and let their imaginations run wild.
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late