Chrystal Street Repair Update Week 9

Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will be completed over the next two to three weeks.
|
Important dates |
Activity |
Impact to residents |
Affected households |
|
Monday, 13 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Tuesday, 14 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Wednesday, 15 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Thursday, 16 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Friday, 17 June 2022 |
Footpath construction |
No on street parking |
All households |
Take a look at what is happening around Richmond
Rainwater Garden Planting Session on Stanmore Road
Rainwater Garden Brings Beauty to Busy Road
Mayoral Candidate/ Mural Painting Event a Success
We Are Richmond team encourages locals to meet political candidates and paint!
Second Community Painting Event at Vogel Street Alleyway a Success
We Are Richmond team encourages local families to get their artist on for a second time
Families Brighten Up the Vogel Street Alleyway
We Are Richmond team encourages local families to get their artist on