Chrystal Street Repair Update Week 9

Jun 13, 2022 | Roading in Richmond

Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will be completed over the next two to three weeks.

 

Important dates

Activity

Impact to residents

Affected households

Monday, 13 June 2022

Footpath construction

No on street parking

All households

Tuesday, 14 June 2022

Footpath construction

No on street parking

All households

Wednesday, 15 June 2022

Footpath construction

No on street parking

All households

Thursday, 16 June 2022

Footpath construction

No on street parking

All households

Friday, 17 June 2022

Footpath construction

No on street parking

All households

 

Take a look at what is happening around Richmond

New Richmond Village Sign Completed

New Richmond Village Sign Completed

What's in a Sign? Well, a lot! After years of deteriorating in the elements, having broken and faded signs, and causing the shopping centre to look run down, We are Richmond decided to do something about the Richmond Village Sign. The shopping centre has no body...

read more
Stanmore Rd/ Swanns Corner Loved and Refreshed

Stanmore Rd/ Swanns Corner Loved and Refreshed

A group of volunteers from We are Richmond and Peter from River conservation nz helped clean up the overgrown and unloved Stanmore/Swanns Rd corner.  Foliage was removed, tidied, cut and the bench seats power-washed and re-stained. Thank you to Keita from Done N...

read more
Richmond Gala 2024–What a Fantastic Day Out!

Richmond Gala 2024–What a Fantastic Day Out!

The Richmond Gala wan an amazing community day. We appreciate everyone coming out and joining in. What amazing work done with all of the massive effort from Avebury House,  Richmond Community Garden, and Riverlution We are Richmond is in charge of coordinating the...

read more