Chrystal Street Repair Update Week 9

Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will be completed over the next two to three weeks.
Important dates |
Activity |
Impact to residents |
Affected households |
Monday, 13 June 2022 |
Footpath construction |
No on street parking |
All households |
Tuesday, 14 June 2022 |
Footpath construction |
No on street parking |
All households |
Wednesday, 15 June 2022 |
Footpath construction |
No on street parking |
All households |
Thursday, 16 June 2022 |
Footpath construction |
No on street parking |
All households |
Friday, 17 June 2022 |
Footpath construction |
No on street parking |
All households |
Take a look at what is happening around Richmond
Petrie Park BBQ & Planting Event
The Richmond community gathered at a bbq at Petrie Park to spend time together but also engage on what they would like to see on the former bowling green at the southern half of the park.
RRBA Installs Wayfinding Signs at Swanns Road Parklet
After graffiti damage, these wayfinding community signs have a new lease of life and are now up at the Swanns Road Parklet!
Zero Data–Essential websites you can browse Data-Free!
Did you know you can access multiple governmental, school and other essential websites even if you’re out of mobile data? All you need is a device connected to the Spark, Skinny, One NZ, 2degrees, Warehouse Mobile, Slingshot or Orcon mobile networks. The purpose of...
Petrie Park Update December 2023
Petrie Park bowling green remediation is underway and progressing. Hayley Guglietta gives us an update.