Chrystal Street Repair Update Week 9
Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will be completed over the next two to three weeks.
Important dates |
Activity |
Impact to residents |
Affected households |
Monday, 13 June 2022 |
Footpath construction |
No on street parking |
All households |
Tuesday, 14 June 2022 |
Footpath construction |
No on street parking |
All households |
Wednesday, 15 June 2022 |
Footpath construction |
No on street parking |
All households |
Thursday, 16 June 2022 |
Footpath construction |
No on street parking |
All households |
Friday, 17 June 2022 |
Footpath construction |
No on street parking |
All households |
Take a look at what is happening around Richmond
Zero Data–Essential websites you can browse Data-Free!
Did you know you can access multiple governmental, school and other essential websites even if you’re out of mobile data? All you need is a device connected to the Spark, Skinny, One NZ, 2degrees, Warehouse Mobile, Slingshot or Orcon mobile networks. The purpose of...
Petrie Park Update December 2023
Petrie Park bowling green remediation is underway and progressing. Hayley Guglietta gives us an update.
RRBA Installs Wayfinding Signs at Swanns Road Parklet
After graffiti damage, these wayfinding community signs have a new lease of life and are now up at the Swanns Road Parklet!
Elmer Elephant Trail Opening Event for Laura Fergusson Brain Injury Trust
The RRBA were honoured to attend Elmer’s Ōtautahi Elephant Trail opening Thursday night and see all of the amazing elephant designs.