Chrystal Street Repair Update Week 9

Jun 13, 2022 | Roading in Richmond

Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will be completed over the next two to three weeks.

 

Important dates

Activity

Impact to residents

Affected households

Monday, 13 June 2022

Footpath construction

No on street parking

All households

Tuesday, 14 June 2022

Footpath construction

No on street parking

All households

Wednesday, 15 June 2022

Footpath construction

No on street parking

All households

Thursday, 16 June 2022

Footpath construction

No on street parking

All households

Friday, 17 June 2022

Footpath construction

No on street parking

All households

 

Take a look at what is happening around Richmond

Petrie Park BBQ & Planting Event

Petrie Park BBQ & Planting Event

The Richmond community gathered at a bbq at Petrie Park to spend time together but also engage on what they would like to see on the former bowling green at the southern half of the park.

read more
Spring Fair 2023 Was a Success!

Spring Fair 2023 Was a Success!

The RRBA had a fabulous day helping run the Spring Fair alongside Avebury House and Richmond Community Garden. They helped activate the children’s play area and also interacted with the public at their infomation stall.

read more