Chrystal Street Repair Update Week 9

Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will be completed over the next two to three weeks.
Important dates |
Activity |
Impact to residents |
Affected households |
Monday, 13 June 2022 |
Footpath construction |
No on street parking |
All households |
Tuesday, 14 June 2022 |
Footpath construction |
No on street parking |
All households |
Wednesday, 15 June 2022 |
Footpath construction |
No on street parking |
All households |
Thursday, 16 June 2022 |
Footpath construction |
No on street parking |
All households |
Friday, 17 June 2022 |
Footpath construction |
No on street parking |
All households |
Take a look at what is happening around Richmond
Swanns Road Parklet Working Bee Part 2
The RRBA co-hosted a wonderful planting event at Swanns Road Parklet again midweek this time.
Swanns Road Parklet Working Bee Part 1
The RRBA co-hosted a wonderful planting event at Swanns Road Parklet
Adventure Avenue Wander/ Walking Festival
The Richmond community gathered at a bbq at Petrie Park to spend time together but also engage on what they would like to see on the former bowling green at the southern half of the park.
30km/hr Speed Reduction in Richmond–Safe Speed Neighbourhoods
Richmond has been the first suburb to change to 30km per hour speeds on certain streets. Why?