Chrystal Street Repair Update Week 9

Jun 13, 2022 | Roading in Richmond

Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will be completed over the next two to three weeks.

 

Important dates

Activity

Impact to residents

Affected households

Monday, 13 June 2022

Footpath construction

No on street parking

All households

Tuesday, 14 June 2022

Footpath construction

No on street parking

All households

Wednesday, 15 June 2022

Footpath construction

No on street parking

All households

Thursday, 16 June 2022

Footpath construction

No on street parking

All households

Friday, 17 June 2022

Footpath construction

No on street parking

All households

 

Take a look at what is happening around Richmond