Chrystal Street Repair Update Week 9

Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will be completed over the next two to three weeks.
|
Important dates |
Activity |
Impact to residents |
Affected households |
|
Monday, 13 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Tuesday, 14 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Wednesday, 15 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Thursday, 16 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Friday, 17 June 2022 |
Footpath construction |
No on street parking |
All households |
Take a look at what is happening around Richmond
30km/hr Speed Reduction in Richmond–Safe Speed Neighbourhoods
Richmond has been the first suburb to change to 30km per hour speeds on certain streets. Why?
The Critic Sports Bar Opening at Richmond Club, The Borough
The RRBA were honoured to attend Elmer’s Ĺtautahi Elephant Trail opening Thursday night and see all of the amazing elephant designs.
Swanns Road Parklet Working Bee Part 2
The RRBA co-hosted a wonderful planting event at Swanns Road Parklet again midweek this time.
Swanns Road Parklet Working Bee Part 1
The RRBA co-hosted a wonderful planting event at Swanns Road Parklet