Petrie / Stapletons / Randall St roadworks

Email update message from Mike Downs (contractor for this work) from Thursday May 9th 2019.
As always, any queries or concerns with this specific work please contact Mike directly or for general concerns via the Richmond residents and business association.
by Craig Given.
Hi Team,
We have approval to reconstruct the last block of Randall Street from Stapletons Rd to Petrie St which will commence on Monday (13th May), weather permitting. I did a letterbox drop for this today (copy attached) advising that we will be closing this block of Randall Street including the Petrie / Randall St intersection from Monday 13th May until we seal these roads in July. Residents will still have access and detours will be clearly signed via Stapletons Rd and Chrystal St.
Also letting you know that the construction work on Chrystal St will be finished by early next week with sealing and asphalting likely to be later next week due to the rain forecast for Sunday & Monday – photos attached.
The planting on Randall St is progressing well – see attached photos. Trees will also be planted will also in Petrie Street early next week.
Kind Regards,
Mike
What other projects are the RR&BA working on?
Meet-Your-Neighbours Tidy Up Session at Medway Parklet
The Medway Parklet needed a good tidy and local neighbours wanted to meet to see if they could maintain this area in the future.
Vape Information Community Talk
Anna Stewart of Vape-Free Kids NZ spoke to the community about vape’s effects and regulations in New Zealand.
Spring Fair 2025
The RRBA had a fabulous day helping run the Spring Fair alongside Avebury House and Richmond Community Garden. They helped activate the children’s play area and also interacted with the public at their infomation stall.
Meet-the-Candidates for Central Ward Councillor
Meet the Candidates for Central Ward Councillor candidates was a successful evening, co-hosted by Sunrise Rotary, We are Richmond and Phillipstown Hub