Petrie / Stapletons / Randall St roadworks
Email update message from Mike Downs (contractor for this work) from Thursday May 9th 2019.
As always, any queries or concerns with this specific work please contact Mike directly or for general concerns via the Richmond residents and business association.
by Craig Given.
Hi Team,
We have approval to reconstruct the last block of Randall Street from Stapletons Rd to Petrie St which will commence on Monday (13th May), weather permitting. I did a letterbox drop for this today (copy attached) advising that we will be closing this block of Randall Street including the Petrie / Randall St intersection from Monday 13th May until we seal these roads in July. Residents will still have access and detours will be clearly signed via Stapletons Rd and Chrystal St.
Also letting you know that the construction work on Chrystal St will be finished by early next week with sealing and asphalting likely to be later next week due to the rain forecast for Sunday & Monday – photos attached.
The planting on Randall St is progressing well – see attached photos. Trees will also be planted will also in Petrie Street early next week.
Kind Regards,
Mike
What other projects are the RR&BA working on?
Roadworks Update for Nicholls Street 6
Traffic: Traffic on both Nicholls Street and Dudley street are set up as one-way, and no entry permitted on NorthAvon Road and Stapleton Road. Inconvenience: Property access including residents on East side of Nicholls st. Disruption Management: Our plan includes...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 6
Stapletons Road (Warden St to Shirley Rd). COMPLETED Completed the final kerb pour Subbase construction now fully complete LOOK AHEAD Complete all footpath construction ready for asphalt Complete basecourse construction Delays None Take a look at what is happening...
Minutes February 2024
Meeting held at Avebury House Tuesday, 27 February 2024 Present:Committee Members: C. Carter, D. Duffy, H. Guglietta (Chair), L. van Bruchem, R. Crawford, C. GivenGovernment Representatives: J. McLellan (Councillor, Central Ward), J. Miller (Community Board,...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 5
Stapletons Road (Warden St to Shirley Rd). COMPLETED Begun the Shirley Road/Stapletons Road intersection construction. Completed the second stage of road construction up to Shirley Road. Completed the Western side footpath works up to Shirley Road LOOK AHEAD Complete...