Petrie Street Repair Update Week 11

This week sees two important milestones. The connection of the water main on North Avon Road and commencing the road construction.
The road construction is key to delivering the project on time so expect some additional resource to arrive to site to help with these operations. This is also when the highest number of plants movement occur. We will be constructing the entire westside of the road, then moving traffic over onto the unsealed road. The process then re-starts on the east side. It is expected to take 4 weeks to get the entire road excavated and backfilled. Sealing will take place in Late September.
We are also, weather permitting, anticipating sealing the footpath and driveways on the westside of Petrie which will be nice to start offering some areas back to residents.
As Always, If you have any concerns about parking, deliveries you may be expecting or access/egress issues please see our STMS. Our STMS is the team member in the Green Hi-Vis. He or she will address any of to your concerns
Photos courtesy of Cillin Corbett, Senior Project Manager, Corde
Take a look at what is happening around Richmond
Richmond Gala 2025
So much fun at Richmond Gala! Co-hosted with Avebury House and Richmond Community Garden, the Children’s Play Area (facilitated by We are Richmond) is always popular in Avebury Park.
Petrie Park BBQ and Consultation 2025
We hosted a BBQ for Petrie Park and an open consultation for the planting plan.
Te Oraka Community Pools Co-Hosted Cleanup 1
Volunteers from different Shirley, Richmond and Dallington had a first cleanup session at Te Oraka Community Pools
Walking Weedathon 4
A multi-area walking Weedathon around the streets of Richmond!