Petrie Street Repair Update Week 12
The aim of the following week will be to complete the entire road excavation. Residents will be moved the West side of the street as we progress with the road construction on the East side.
Last week the footpath contained too much moisture for Asphalt sealing, so we are anticipating sealing later this week. Pedestrians will then be moved to the new footpath and we will remove the East side infrastructure at the same time as the road excavation.
As always, If you have any concerns about parking, deliveries you may be expecting or access/egress issues please see our STMS. Our STMS is the team member in the Green Hi-Vis. He or she will address any of to your concerns
Take a look at what is happening around Richmond
Zero Data–Essential websites you can browse Data-Free!
Did you know you can access multiple governmental, school and other essential websites even if you’re out of mobile data? All you need is a device connected to the Spark, Skinny, One NZ, 2degrees, Warehouse Mobile, Slingshot or Orcon mobile networks. The purpose of...
Petrie Park Update December 2023
Petrie Park bowling green remediation is underway and progressing. Hayley Guglietta gives us an update.
RRBA Installs Wayfinding Signs at Swanns Road Parklet
After graffiti damage, these wayfinding community signs have a new lease of life and are now up at the Swanns Road Parklet!
Elmer Elephant Trail Opening Event for Laura Fergusson Brain Injury Trust
The RRBA were honoured to attend Elmer’s Ōtautahi Elephant Trail opening Thursday night and see all of the amazing elephant designs.