Petrie Street Repair Update Week 12
![20220805_110927](https://wearerichmond.co.nz/wp-content/uploads/2022/08/20220805_110927-1-rotated.jpg)
The aim of the following week will be to complete the entire road excavation. Residents will be moved the West side of the street as we progress with the road construction on the East side.
Last week the footpath contained too much moisture for Asphalt sealing, so we are anticipating sealing later this week. Pedestrians will then be moved to the new footpath and we will remove the East side infrastructure at the same time as the road excavation.
As always, If you have any concerns about parking, deliveries you may be expecting or access/egress issues please see our STMS. Our STMS is the team member in the Green Hi-Vis. He or she will address any of to your concerns
![Screenshot 2022-08-08 at 10-32-12 wearerichmond.co.nz Mail - Week 12 Update Petrie Street](https://wearerichmond.co.nz/wp-content/uploads/2022/08/Screenshot-2022-08-08-at-10-32-12-wearerichmond.co_.nz-Mail-Week-12-Update-Petrie-Street.png)
Take a look at what is happening around Richmond
Swanns Road Parklet Working Bee Part 2
The RRBA co-hosted a wonderful planting event at Swanns Road Parklet again midweek this time.
Swanns Road Parklet Working Bee Part 1
The RRBA co-hosted a wonderful planting event at Swanns Road Parklet
Adventure Avenue Wander/ Walking Festival
The Richmond community gathered at a bbq at Petrie Park to spend time together but also engage on what they would like to see on the former bowling green at the southern half of the park.
30km/hr Speed Reduction in Richmond–Safe Speed Neighbourhoods
Richmond has been the first suburb to change to 30km per hour speeds on certain streets. Why?
![](https://wearerichmond.co.nz/wp-content/uploads/2022/07/Screenshot-2022-07-04-at-09-53-59-wearerichmond.co_.nz-Mail-Week-7-Update.png)
![](https://wearerichmond.co.nz/wp-content/uploads/2022/08/20220808_085354-scaled.jpg)