Petrie Street Repair Update Week 12
The aim of the following week will be to complete the entire road excavation. Residents will be moved the West side of the street as we progress with the road construction on the East side.
Last week the footpath contained too much moisture for Asphalt sealing, so we are anticipating sealing later this week. Pedestrians will then be moved to the new footpath and we will remove the East side infrastructure at the same time as the road excavation.
As always, If you have any concerns about parking, deliveries you may be expecting or access/egress issues please see our STMS. Our STMS is the team member in the Green Hi-Vis. He or she will address any of to your concerns
Take a look at what is happening around Richmond
Petrie Park Barbecue – Summer with your Neighbours
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late
Activities at Richmond Working Men’s Club
Did you know the Richmond Working Men’s club has a Pigeon club!?
Cycle or walk the river
Jump on the Avon – Otakaro cycle/walkway and enjoy nature
Yoga At Avebury
Come down to Avebury House to enjoy yoga with Dakota.