Petrie Street Repair Update Week 16
The aim of this week will be to finish the Eastern side, and also planning for preparing the road for its final surface .
Pedestrians will remain on the new footpath on the East side.
As Always, if you have any concerns about parking, deliveries you may be expecting, or access/egress issues please see our STMS. Our STMS is the team member in the Green Hi-Vis. He or she will address any of to your concerns
Take a look at what is happening around Richmond
Planting for the Future
Over 360 Pareawa Banks Avenue students and local organisations come together to plant trees for the future.
Rainwater Garden Planting Session on Stanmore Road
Rainwater Garden Brings Beauty to Busy Road
Mayoral Candidate/ Mural Painting Event a Success
We Are Richmond team encourages locals to meet political candidates and paint!
Second Community Painting Event at Vogel Street Alleyway a Success
We Are Richmond team encourages local families to get their artist on for a second time