Petrie Street Repair Update Week 18
The aim of the following week will be to finish the road construction and complete its final surface .
The road closure should only remain in place for 2 more weeks. In the last week, we will complete the line marking and final touch-ups for the handover back to the CCC.
Pedestrians can remain on both new footpaths.
As Always, if you have any concerns about parking, deliveries you may be expecting, or access/egress issues please see our STMS. Our STMS is the team member in the Green Hi-Vis. He or she will address any of to your concerns
Take a look at what is happening around Richmond
Planting for the Future
Over 360 Pareawa Banks Avenue students and local organisations come together to plant trees for the future.
Rainwater Garden Planting Session on Stanmore Road
Rainwater Garden Brings Beauty to Busy Road
Mayoral Candidate/ Mural Painting Event a Success
We Are Richmond team encourages locals to meet political candidates and paint!
Second Community Painting Event at Vogel Street Alleyway a Success
We Are Richmond team encourages local families to get their artist on for a second time
Families Brighten Up the Vogel Street Alleyway
We Are Richmond team encourages local families to get their artist on
Avon Hub Now Open in Former Spartan Sport Hall
The Avon Hub held an open day 22 May to show the community the sport and meeting facilities now available.