Petrie Street Repair Update Week 17

Sep 11, 2022 | Roading in Richmond

Unfortunately, the footpath asphalt couldn’t get completed this week due to the moisture in the materials. We have reprogramed this for Monday–dependent on the weekend’s weather.

The aim of this week will be to finish the Eastern side and preparing the road for its final surface .

Pedestrians will remain on the new footpath on the Western side.

As Always, if you have any concerns about parking, deliveries you may be expecting, or access/egress issues please see our STMS. Our STMS is the team member in the Green Hi-Vis. He or she will address any of to your concerns

Take a look at what is happening around Richmond

Petrie Park BBQ & Planting Event

Petrie Park BBQ & Planting Event

The Richmond community gathered at a bbq at Petrie Park to spend time together but also engage on what they would like to see on the former bowling green at the southern half of the park.

read more
Spring Fair 2023 Was a Success!

Spring Fair 2023 Was a Success!

The RRBA had a fabulous day helping run the Spring Fair alongside Avebury House and Richmond Community Garden. They helped activate the children’s play area and also interacted with the public at their infomation stall.

read more