Petrie Street Repair Update Week 3
Week 3 see’s our drainage team pass the 50% complete mark for the new stormwater line. The team will continue straight down Petrie toward No.13. At times this will involve trenching past residents driveways so expect a knock from our friendly staff the evening or morning prior to any works. Access will be reinstated to each household before the evenings work is completed.
The Streetscape team will continue to remove kerb and footpath at the top of Petrie. Once the material is removed we will continue to backfill with fresh aggregate and start shaping the future footpath alignment.
You will notice the site becoming busier this week. If you have any concerns about parking, deliveries you may be expecting or access/egress issues please see our STMS. Our STMS is the team member in the Green Hi-Vis. He or she will address any of to your concerns.
|
|||
Important dates |
Activity |
Impact to residents |
Affected households |
Monday, 6th June 2022 |
Public Holiday |
One Way system Northbound between North Avon and Randall. Driveway access maintained throughout |
All Residents |
|
|
||
Tuesday, 7th June 2022 |
New 300mm Underchannel Stormwater Pipe |
One Way system Northbound between North Avon and Randall. Driveway access maintained throughout |
Crossing Residents driveways between No. 21B to No.15A |
Kerb & Footpath Removal |
Footpath closed on the West Side of Petrie |
||
Wednesday, 8th June 2022 |
New 300mm Underchannel Stormwater Pipe |
One Way system Northbound between North Avon and Randall. Driveway access maintained throughout |
Crossing Residents driveways between No. 21B to No.15A |
Kerb & Footpath Removal |
Footpath closed on the West Side of Petrie |
||
Thursday, 9th June 2022 |
New 300mm Underchannel Stormwater Pipe |
One Way system Northbound between North Avon and Randall. Driveway access maintained throughout |
Crossing Residents driveways between No. 21B to No.15A |
Kerb & Footpath Removal |
Footpath closed on the West Side of Petrie |
||
Friday, 10th June 2022 |
New 300mm Underchannel Stormwater Pipe |
One Way system Northbound between North Avon and Randall. Driveway access maintained throughout |
Crossing Residents driveways between No. 21B to No.15A |
Kerb & Footpath Removal |
Footpath closed on the West Side of Petrie |
Take a look at what is happening around Richmond
Zero Data–Essential websites you can browse Data-Free!
Did you know you can access multiple governmental, school and other essential websites even if you’re out of mobile data? All you need is a device connected to the Spark, Skinny, One NZ, 2degrees, Warehouse Mobile, Slingshot or Orcon mobile networks. The purpose of...
Petrie Park Update December 2023
Petrie Park bowling green remediation is underway and progressing. Hayley Guglietta gives us an update.
RRBA Installs Wayfinding Signs at Swanns Road Parklet
After graffiti damage, these wayfinding community signs have a new lease of life and are now up at the Swanns Road Parklet!
Elmer Elephant Trail Opening Event for Laura Fergusson Brain Injury Trust
The RRBA were honoured to attend Elmer’s Ōtautahi Elephant Trail opening Thursday night and see all of the amazing elephant designs.