Petrie Street Repair Update Week 3

Week 3 see’s our drainage team pass the 50% complete mark for the new stormwater line. The team will continue straight down Petrie toward No.13. At times this will involve trenching past residents driveways so expect a knock from our friendly staff the evening or morning prior to any works. Access will be reinstated to each household before the evenings work is completed.
The Streetscape team will continue to remove kerb and footpath at the top of Petrie. Once the material is removed we will continue to backfill with fresh aggregate and start shaping the future footpath alignment.
You will notice the site becoming busier this week. If you have any concerns about parking, deliveries you may be expecting or access/egress issues please see our STMS. Our STMS is the team member in the Green Hi-Vis. He or she will address any of to your concerns.
|
|
|||
|
Important dates |
Activity |
Impact to residents |
Affected households |
|
Monday, 6th June 2022 |
Public Holiday |
One Way system Northbound between North Avon and Randall. Driveway access maintained throughout |
All Residents |
|
|
|
||
|
Tuesday, 7th June 2022 |
New 300mm Underchannel Stormwater Pipe |
One Way system Northbound between North Avon and Randall. Driveway access maintained throughout |
Crossing Residents driveways between No. 21B to No.15A |
|
Kerb & Footpath Removal |
Footpath closed on the West Side of Petrie |
||
|
Wednesday, 8th June 2022 |
New 300mm Underchannel Stormwater Pipe |
One Way system Northbound between North Avon and Randall. Driveway access maintained throughout |
Crossing Residents driveways between No. 21B to No.15A |
|
Kerb & Footpath Removal |
Footpath closed on the West Side of Petrie |
||
|
Thursday, 9th June 2022 |
New 300mm Underchannel Stormwater Pipe |
One Way system Northbound between North Avon and Randall. Driveway access maintained throughout |
Crossing Residents driveways between No. 21B to No.15A |
|
Kerb & Footpath Removal |
Footpath closed on the West Side of Petrie |
||
|
Friday, 10th June 2022 |
New 300mm Underchannel Stormwater Pipe |
One Way system Northbound between North Avon and Randall. Driveway access maintained throughout |
Crossing Residents driveways between No. 21B to No.15A |
|
Kerb & Footpath Removal |
Footpath closed on the West Side of Petrie |
Take a look at what is happening around Richmond
Richmond Gala 2025
So much fun at Richmond Gala! Co-hosted with Avebury House and Richmond Community Garden, the Children’s Play Area (facilitated by We are Richmond) is always popular in Avebury Park.
Petrie Park BBQ and Consultation 2025
We hosted a BBQ for Petrie Park and an open consultation for the planting plan.
Te Oraka Community Pools Co-Hosted Cleanup 1
Volunteers from different Shirley, Richmond and Dallington had a first cleanup session at Te Oraka Community Pools
Walking Weedathon 4
A multi-area walking Weedathon around the streets of Richmond!