Petrie Street Repair Update Week 3
Week 3 see’s our drainage team pass the 50% complete mark for the new stormwater line. The team will continue straight down Petrie toward No.13. At times this will involve trenching past residents driveways so expect a knock from our friendly staff the evening or morning prior to any works. Access will be reinstated to each household before the evenings work is completed.
The Streetscape team will continue to remove kerb and footpath at the top of Petrie. Once the material is removed we will continue to backfill with fresh aggregate and start shaping the future footpath alignment.
You will notice the site becoming busier this week. If you have any concerns about parking, deliveries you may be expecting or access/egress issues please see our STMS. Our STMS is the team member in the Green Hi-Vis. He or she will address any of to your concerns.
|
|||
Important dates |
Activity |
Impact to residents |
Affected households |
Monday, 6th June 2022 |
Public Holiday |
One Way system Northbound between North Avon and Randall. Driveway access maintained throughout |
All Residents |
|
|
||
Tuesday, 7th June 2022 |
New 300mm Underchannel Stormwater Pipe |
One Way system Northbound between North Avon and Randall. Driveway access maintained throughout |
Crossing Residents driveways between No. 21B to No.15A |
Kerb & Footpath Removal |
Footpath closed on the West Side of Petrie |
||
Wednesday, 8th June 2022 |
New 300mm Underchannel Stormwater Pipe |
One Way system Northbound between North Avon and Randall. Driveway access maintained throughout |
Crossing Residents driveways between No. 21B to No.15A |
Kerb & Footpath Removal |
Footpath closed on the West Side of Petrie |
||
Thursday, 9th June 2022 |
New 300mm Underchannel Stormwater Pipe |
One Way system Northbound between North Avon and Randall. Driveway access maintained throughout |
Crossing Residents driveways between No. 21B to No.15A |
Kerb & Footpath Removal |
Footpath closed on the West Side of Petrie |
||
Friday, 10th June 2022 |
New 300mm Underchannel Stormwater Pipe |
One Way system Northbound between North Avon and Randall. Driveway access maintained throughout |
Crossing Residents driveways between No. 21B to No.15A |
Kerb & Footpath Removal |
Footpath closed on the West Side of Petrie |
Take a look at what is happening around Richmond
Families Brighten Up the Vogel Street Alleyway
We Are Richmond team encourages local families to get their artist on
Avon Hub Now Open in Former Spartan Sport Hall
The Avon Hub held an open day 22 May to show the community the sport and meeting facilities now available.
Cultivate comes to Richmond
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late
Adventure Ave, a family-friendly environmental playground for kids to enjoy and let their imaginations run wild.
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late