Petrie Street Repair Update Week 4
Week four sees us getting closer to the end of the street with the Stormwater drainage. The final 80 metres of this pipeline is reinforced concrete so this takes a bit longer as there’s some added detailing involved and concrete pouring around the pipe. Nevertheless, we expect to be down to the last 20m stretch by Friday.
Our behind kerb streetscape crew are busy removing the existing infrastructure and they’re working towards reinstating the first new kerb, planned for Friday.
If you have any concerns about parking, deliveries you may be expecting or access/egress issues please see our STMS. Our STMS is the team member in the Green Hi-Vis. He or she will address any of to your concerns
Week 4: | |||
Important dates | Activity | Impact to residents | Affected households |
Monday, 13 June 2022 | New 300mm Underchannel Stormwater Pipe | One Way system Northbound between North Avon and Randall. Driveway access maintained throughout | All Residents |
Kerb & Footpath Removal | |||
Tuesday, 14 June 2022 | New 300mm Underchannel Stormwater Pipe | One Way system Northbound between North Avon and Randall. Driveway access maintained throughout | All Residents |
Kerb & Footpath Removal | |||
Wednesday, 15 June 2022 | New 300mm Underchannel Stormwater Pipe | One Way system Northbound between North Avon and Randall. Driveway access maintained throughout | All Residents |
Kerb & Footpath Removal | |||
Thursday, 16 June 2022 | New 300mm Underchannel Stormwater Pipe | One Way system Northbound between North Avon and Randall. Driveway access maintained throughout | All Residents |
Kerb & Footpath Removal | |||
Friday, 17 June 2022 | New 300mm Underchannel Stormwater Pipe | One Way system Northbound between North Avon and Randall. Driveway access maintained throughout | All Residents |
Two Concrete Pours | |||
Kerb & Footpath Removal |
Take a look at what is happening around Richmond
Petrie Park Mural Painting Event 3
Our second Petrie Park mural painting day with the community was a success, and even the dogs came along!
Petrie Park Mural Painting Event 2
Our second Petrie Park mural painting day with the community was a success, and even the dogs came along!
Petrie Park Mural Painting Event I
We had our first mural painting day with the community and it was a success!
Matariki 2024 — A Day and Night of Connection
Matariki in the Zone was a wonderful day and evening out for our community. A big thank you to Avon-Ōtākaro Network Richmond Community Garden and Avebury House for running this every year! We are Richmond hopped on the bandwagon to help out more this year. So...