Petrie Street Repair Update Week 4

Jun 13, 2022 | Roading in Richmond

Week four sees us getting closer to the end of the street with the Stormwater drainage. The final 80 metres of this pipeline is reinforced concrete so this takes a bit longer as there’s some added detailing involved and concrete pouring around the pipe. Nevertheless, we expect to be down to the last 20m stretch by Friday.

Our behind kerb streetscape crew are busy removing the existing infrastructure and they’re working towards reinstating the first new kerb, planned for Friday.

If you have any concerns about parking, deliveries you may be expecting or access/egress issues please see our STMS. Our STMS is the team member in the Green Hi-Vis. He or she will address any of to your concerns

 

Week 4:      
Important dates Activity Impact to residents Affected households
Monday, 13 June 2022 New 300mm Underchannel Stormwater Pipe One Way system Northbound between North Avon and Randall. Driveway access maintained throughout All Residents
Kerb & Footpath Removal
Tuesday, 14 June 2022 New 300mm Underchannel Stormwater Pipe One Way system Northbound between North Avon and Randall. Driveway access maintained throughout All Residents
Kerb & Footpath Removal
Wednesday, 15 June 2022 New 300mm Underchannel Stormwater Pipe One Way system Northbound between North Avon and Randall. Driveway access maintained throughout All Residents
Kerb & Footpath Removal
Thursday, 16 June 2022 New 300mm Underchannel Stormwater Pipe One Way system Northbound between North Avon and Randall. Driveway access maintained throughout All Residents
Kerb & Footpath Removal
Friday, 17 June 2022 New 300mm Underchannel Stormwater Pipe One Way system Northbound between North Avon and Randall. Driveway access maintained throughout All Residents
Two Concrete Pours
Kerb & Footpath Removal

Take a look at what is happening around Richmond

Zero Data–Essential websites you can browse Data-Free!

Zero Data–Essential websites you can browse Data-Free!

Did you know you can access multiple governmental, school and other essential websites even if you’re out of mobile data? All you need is a device connected to the Spark, Skinny, One NZ, 2degrees, Warehouse Mobile, Slingshot or Orcon mobile networks. The purpose of...

read more