Richmond Roading Update 2023
The representatives of the Richmond Residents and Business Association met recently with the Transport and Roading Group at the Christchurch City Council and we are now able to pass on the following information………………
UPDATE ON IMPROVING THE RICHMOND ROADING NETWORK
FULL ROAD RENEWALS 1 – NICHOLLS AND DUDLEY STREETS
Tender process completed by 30 May, 2023
Construction start 1 July, 2023
Construction end 30 November, 2023
FULL ROAD RENEWALS 2 – STAPLETONS ROAD – WARDEN STREET TO SHIRLEY ROAD
Tender process completed by 30 May, 2023
Construction start 1 July, 2023
Construction end 30 September, 2023
RICHMOND CRAF* PROJECTS
Intersection upgrade at Averill Street and Petrie Street
Intersection upgrade at Averill Street and Stapletons Road
Intersection upgrade at Chancellor Street and Guild Street
Intersection upgrade at Guild Street and Hills Road
Intersection upgrade at Guild Street and Slater Street
New kerb and channel on Slater Street from Guild Street to 75/80 Slater
(currently no delineation between road and footpath)
New speed hump on Slater Street at the Warden Street intersection
New speed hump on Chancellor Street at the Warden Street intersection
New speed hump on Dudley Street at the Slater Street intersection
Slater Street rebuild from Warden Street to Shirley Road
Expected completion date for all of the above – 30 June, 2024
*Christchurch Renewal Amenities Fund (granted by Government in October 2021.)
NEIGHBOURHOOD GREENWAY CYCLEWAY
North Parade, Averill Street, Stapletons Road, Dudley Street, Nicholls Street
Expected completion date – 30 June, 2024
AREA-WIDE SPEED RESTRICTION BETWEEN NORTH AVON ROAD, HILLS ROAD, SHIRLEY ROAD AND
NORTH PARADE
Expected completion date – 30 June, 2023
SLATER STREET REBUILD FROM WARDEN STREET TO SHIRLEY ROAD and no. 80/75
Expected completion date – 30 November, 2024
POULTON AVE
Dates still to be confirmed with pavement maintenance and street trees teams for road resurfacing and tree protection wheel stops work.
All of the above work is supplementary to normal City Council maintenance work. Please use your “Snap, Send, Solve” App to advise the Council of maintenance issues in your street or contact us at secretary@wearerichmond.co.nz>
Take a look at what is happening around Richmond
Planting for the Future
Over 360 Pareawa Banks Avenue students and local organisations come together to plant trees for the future.
Rainwater Garden Planting Session on Stanmore Road
Rainwater Garden Brings Beauty to Busy Road
Mayoral Candidate/ Mural Painting Event a Success
We Are Richmond team encourages locals to meet political candidates and paint!
Second Community Painting Event at Vogel Street Alleyway a Success
We Are Richmond team encourages local families to get their artist on for a second time
Families Brighten Up the Vogel Street Alleyway
We Are Richmond team encourages local families to get their artist on
Avon Hub Now Open in Former Spartan Sport Hall
The Avon Hub held an open day 22 May to show the community the sport and meeting facilities now available.