Stapletons Road (Warden St to Shirley Rd)

  • COMPLETED
    • Drainage completed
    • Western side footpath up to Shirley Road ready for asphalt
    • Excavated Western side of the road to the underside of the road formation and begin road construction
  • LOOK AHEAD
    • Begin excavating carriageway to the underside of the road construction and begin filling – We will likely have 2 more days of this next week.
    • Construct the Eastern side footpath up to Shirley Road ready for asphalt
  • Delays
    • Contaminated material to be removed from site slowing down works.

Corde is happy to receive any feedback or concerns from residents.

Take a look at what is happening around Richmond

Zero Data–Essential websites you can browse Data-Free!

Zero Data–Essential websites you can browse Data-Free!

Did you know you can access multiple governmental, school and other essential websites even if you’re out of mobile data? All you need is a device connected to the Spark, Skinny, One NZ, 2degrees, Warehouse Mobile, Slingshot or Orcon mobile networks. The purpose of...

read more
Petrie Park BBQ & Planting Event

Petrie Park BBQ & Planting Event

The Richmond community gathered at a bbq at Petrie Park to spend time together but also engage on what they would like to see on the former bowling green at the southern half of the park.

read more