Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 2

Feb 14, 2024 | Roading in Richmond, RR&BA

Stapletons Road (Warden St to Shirley Rd)

  • COMPLETED
    • Drainage completed
    • Western side footpath up to Shirley Road ready for asphalt
    • Excavated Western side of the road to the underside of the road formation and begin road construction
  • LOOK AHEAD
    • Begin excavating carriageway to the underside of the road construction and begin filling – We will likely have 2 more days of this next week.
    • Construct the Eastern side footpath up to Shirley Road ready for asphalt
  • Delays
    • Contaminated material to be removed from site slowing down works.

Corde is happy to receive any feedback or concerns from residents.