Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 3

Feb 19, 2024 | Roading in Richmond, RR&BA

Stapletons Road (Warden St to Shirley Rd).

  • COMPLETED
    • Begun excavating carriageway to the underside of the road construction and begin filling
    • Constructed the Eastern side footpath up to Shirley Road ready for asphalt
    •  
  • LOOK AHEAD
    • Continue the road dig out on Stapletons Road
    • Seal the footpath up to Shirley Road on Wednesday 21st February – excluding the current crusher dust footpath
    • Begin the Shirley Road tie in works.
    • Begin constructing the road – This will involve the grader and rollers
    •  
  • Delays
    • None.

Take a look at what is happening around Richmond

Petrie Park BBQ & Planting Event

Petrie Park BBQ & Planting Event

The Richmond community gathered at a bbq at Petrie Park to spend time together but also engage on what they would like to see on the former bowling green at the southern half of the park.

read more
Spring Fair 2023 Was a Success!

Spring Fair 2023 Was a Success!

The RRBA had a fabulous day helping run the Spring Fair alongside Avebury House and Richmond Community Garden. They helped activate the children’s play area and also interacted with the public at their infomation stall.

read more