Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 3
Stapletons Road (Warden St to Shirley Rd).
- COMPLETED
- Begun excavating carriageway to the underside of the road construction and begin filling
- Constructed the Eastern side footpath up to Shirley Road ready for asphalt
- LOOK AHEAD
- Continue the road dig out on Stapletons Road
- Seal the footpath up to Shirley Road on Wednesday 21st February – excluding the current crusher dust footpath
- Begin the Shirley Road tie in works.
- Begin constructing the road – This will involve the grader and rollers
- Delays
- None.
Take a look at what is happening around Richmond
Cultivate comes to Richmond
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late
Adventure Ave, a family-friendly environmental playground for kids to enjoy and let their imaginations run wild.
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late
Petrie Park Barbecue – Summer with your Neighbours
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late
Activities at Richmond Working Men’s Club
Did you know the Richmond Working Men’s club has a Pigeon club!?
Cycle or walk the river
Jump on the Avon – Otakaro cycle/walkway and enjoy nature
Yoga At Avebury
Come down to Avebury House to enjoy yoga with Dakota.